Project Details
- Client
- City of Mansfield
- Location
- Mansfield
- Year
- 2022–2025
- Status
- Completed
- Photos
- 161 photos ↓
Construction of the current Water Treatment Plant (WTP) began in 1947 with the raw water intake structure and pump station at Clear Fork Reservoir. The WTP was built in two phases: the initial phase in 1950 and the second phase in 1968.
The WTP treats a blend of surface and well water using a conventional process that includes pre-oxidation, coagulation, flocculation, sedimentation, granular media filtration, and disinfection. Potassium permanganate is added at the Clear Fork intake structure for pre-oxidation and zebra mussel control. The plant has a capacity of 25 MGD with an average daily flow of 12 MGD. The distribution system consists of over 300 miles of waterlines, 3,400 valves, 24,000 service taps, and 2,290 fire hydrants, providing potable water and fire suppression to nearly 50,000 residents.
Master Plan
The City of Mansfield engaged KEM to develop a master plan for upgrading its water treatment plant, which had last undergone major process improvements in the 1960s. As part of the plan, KEM identified several systems in need of modernization, including:
- Replacement of gravity sand filters and underdrains.
- Upgrades to the filter piping gallery, incorporating filter-to-waste capabilities and automated backwashing.
- Overhaul of flocculators, featuring the addition of vertical mixers.
- Renovations to sedimentation basins, including new chain and flight collectors and effluent launders.
- Rehabilitation of the influent flume leading to the flocculators.
- Conversion of disinfection methods from chlorine gas to sodium hypochlorite.
- Enhancements to the alum and caustic feed systems.
- Relocation of the carbon feed system from the treatment plant to the raw water pump station.
- Installation of new raw water pumps and high-service pumps.
- Electrical and instrumentation & control upgrades.
Design and Construction
Due to the project's compressed timeline, KEM implemented a Construction Manager at Risk (CMAR) approach, enabling a contractor to be selected and construction to commence in a phased manner as design progressed. Construction for Phases 1–3 began in late 2021, with all improvements expected to be completed by early 2025.
This project includes the rehabilitation, repair, and replacement of critical assets, including but not limited to:
- Asbestos abatement.
- Painting and coating assets.
- Repair of the raw water intake flume.
- Complete sedimentation/flocculation basin redesign with replacement of all mechanical/electrical components.
- Filter improvements that include a new air scour backwash system, replacement of all valves, rehab of all pipe, filter reconfiguration, and placement of new filter media.
- Structural repairs and pump rehabilitation at the Raw Water Pump Station and the WTP.
- Pretreatment and chemical feed system improvements.
- Replacement of high service pumps and filter backwash pumps.
- Upgrades to the WTP’s HVAC systems.
- SCADA control of assets.
- Complete roof replacement.
- Secondary access to the Plant.