Following a sanitary evaluation, KEM recommended increasing both the diameter and depth of the sanitary mains, along with upgrades to the primary pump station, and designed the improvements.
KEM submitted, received and administered a Water & Wastewater Infrastructure Grant for the project through the Ohio Department of Development. The grant covered 90% of project costs and was for $1.47M
The project included approximately 3,350 linear feet of 12-inch gravity sewer, 810 linear feet of 4-inch force main and 420 linear feet of 2-inch force main, along with two prepackaged pump stations and all associated electrical and control work. Each pump station has submersible pumps, guide rail systems, motors and control panels, and the new primary pump station’s structures are sized to accommodate larger pumps as development progresses.
Bids were opened on July 16, 2025, against an engineer’s estimate of $1,672,000, and Dirt Dawg Excavating, LLC submitted the low bid of $1,719,482.50. During construction, KEM provided weekly progress updates for the Village. By mid-April 2026 both pump stations were in place, the force main was largely complete and less than 300 feet of 12-inch sewer remained, following an open-cut crossing of State Route 229. Permanent power for the pump stations was installed in June 2026.