Project Details
- Client
- City of Dover
- Location
- Dover
- Year
- 2022
This ODOT District 11 LPA local-let project involved constructing a 1.1-mile, 10-foot-wide multi-use trail along the Tuscarawas River, between South Tuscarawas Avenue and East Avenue. The trail was built with a 5-inch 304 limestone aggregate base on a prepared subgrade, topped with a 1-inch surface of limestone screenings. The project also included the installation of 36 new decorative light poles and luminaires, as well as the construction of several bioretention cells on both sides of the trail and drainage upgrades.