Project Details
- Client
- City of Sandusky
- Location
- Sandusky
- Year
- 2024
- Status
- Completed
- Photos
- 6 photos ↓
The project included the installation of rectangular rapid flashing beacons (RRFBs), school zone flasher assemblies, and traffic signal modifications at Tyler St. Additionally, full signal replacements were completed at Pierce St. and Columbus Ave., involving the installation of new foundations, poles, cabinets, and associated hardware, as well as jack-and-bore metal conduit and power service.
Traffic signal enhancements also incorporated new stop line radar detection and preemption systems, along with new curb ramps, high-visibility crosswalk markings, and minor drainage improvements throughout the project corridor.
A key challenge in this project was ensuring compliance with all relevant accessibility and safety standards while integrating modern signal technology and pedestrian infrastructure improvements.
KEM provided construction inspection services to verify compliance with project plans and contract requirements. Daily written logs of project activity and verification of completed quantities ensured precise documentation.
KEM also monitored subcontractor work efforts and ensured compliance with Disadvantaged Business Enterprise (DBE) requirements. Pay requests were reviewed and approved in the field before submission.
Further responsibilities included approving material submittals, processing change orders, and preparing estimates for the City's approval. Additionally, KEM oversaw concrete foundation placement and conducted quality assurance testing to verify compliance with project specifications.