KEM prepared and submitted an approved General Plan to the Ohio EPA, recommending the drilling of two new wells and the construction of a new WTP on the southeast side of the Village.
The proposed WTP will have a production capacity exceeding twice that of the current facility. Key features include:
- Two new wells
- Iron and manganese pressure filters
- Clearwells
- High-service pumps
- A generator
- An updated control system
Additionally, the project includes replacing all customer water meters, which were originally installed when the system was first developed, ensuring more accurate and reliable readings for the community.