Project Details
- Client
- Richland County
- Location
- Troy Township, Richland County
- Year
- 2026 (expected)
- Status
- Under construction
- Photos
- 51 photos · 7 videos ↓
The single-lane, three-legged roundabout is the same size as the county's Cook Road/Illinois Avenue roundabout, and the Richland B&O Trail crosses the road at the intersection. Adena Corp. of Mansfield is building the project.
The Richland County Engineer identified the intersection as the most dangerous on the busy corridor between Lexington and Ontario. A 2021 safety study of a three-mile stretch of the corridor counted 95 crashes from 2017 to 2019, and the intersection averaged more than six injury crashes a year from 2017 to 2022, including one fatality.
The roundabout was designed by EMHT of Columbus. Adena Corp. submitted the lowest of three bids, $2.44 million, against an engineer's estimate of $2.9 million. Grants from the Ohio Department of Transportation and the Ohio Public Works Commission cover 90% of the construction cost. The work includes two small bridges at the intersection.
Lexington-Springmill Road and Home Road closed on June 15, 2026, for about 120 days, with a signed detour on U.S. 42, Trimble Road and Park Avenue West. The B&O Trail crossing closed on June 30 for 90 days. Completion is expected in fall 2026.