- Client
- City of Mansfield
- Location
- Mansfield
- Year
- 2025
- Status
- Completed
- Photos
- 27 photos · 1 video ↓
The scope of work included removing existing riprap from a previous culvert installation, diverting the creek bed’s water flow to allow for construction, installing a new culvert, and constructing a concrete walking path over the newly placed structure. Concrete footings and wing walls were poured to support the culvert, and more than 200 cubic yards of new riprap were installed to prevent erosion around the structure.
One of the most significant challenges faced during this project was managing the creek’s water flow, which was highly prone to near flash-flood conditions. Heavy rainfall frequently overwhelmed the dam used for bypass pumping, causing substantial delays in progress due to repeated weather events throughout the construction period. Another challenge involved the addition of parking spaces on the west side of the creek—an area not originally included in the project scope. To address this, KEM conducted field measurements to determine a suitable layout for the new parking configuration. This change required modifications to the proposed fencing plan, and KEM adjusted the fence layout and material quantities to better align with the updated design.
Throughout the project, KEM provided daily construction inspection services to ensure compliance with the approved plans and contract requirements. Detailed logs of project activities and verification of completed quantities were maintained. KEM also reviewed and approved material submittals, provided regular progress updates, and prepared pay estimates for the City of Mansfield’s approval.