Southeast Interceptor Sewer, Phase 2, Elyria

KEM is currently delivering design services for the second phase of a three-phase improvement program outlined in the Elyria Facility Plan. The Southeast Interceptor Sewer Project Phase 2 encompasses 7,700 linear feet of sanitary sewer ranging from 8 inches to 30 inches in diameter.

Project Details

Client
City of Elyria
Location
Elyria
Year
Ongoing

This phase includes the installation of a jack-and-bore segment beneath State Route 57 and the construction of 23 manholes.