Project Details
- Client
- City of Ontario
- Location
- Ontario
- Year
- 2018
The project removed the existing slip ramps at both ramp terminals, replacing them with standard right turn lanes and improved radii to create a more predictable and efficient traffic pattern. These modifications were developed to reduce conflict points, support smoother vehicle movements, and bring the intersection into alignment with current design practices.
In addition to geometric upgrades, the project included significant supporting improvements. KEM redesigned and upgraded the existing drainage system to improve stormwater conveyance and long-term performance. The team also reconstructed guardrail to meet current safety standards and updated all signing and pavement markings to provide clearer guidance for motorists. Together, these enhancements deliver a safer, more intuitive, and more reliable intersection for daily traffic and future growth.