Project Details
- Client
- City of Vermilion
- Location
- Vermilion
- Year
- 2020
- Status
- Completed
- Photos
- 12 photos ↓
The scope of work included extensive shoulder repairs, which involved the removal of three-foot-wide sections of the existing shoulders and subbase on both sides of the roadway. These sections were replaced with a new subbase comprising six inches of aggregate base and six inches of asphalt concrete base.
The project also entailed milling and paving the surface and shoulders with 2½ inches of Type 2 Intermediate Course and 1½ inches of Type 1 Asphalt. Additional features included the installation of 2,850 feet of Shallow Pipe Underdrain and 750 feet of Type MGS Guardrail, along with new roadway signage and pavement markings. A notable aspect of the project was the removal of the asphalt wearing course on Bridge #0195 down to the top of the box beams, followed by the installation of a new Type 3 Waterproofing system and a stainless-steel drip edge prior to the placement of two new asphalt layers.