Project Details
- Client
- City of Lorain
- Location
- Lorain
- Year
- 2020
- Status
- Completed
- Photos
- 10 photos ↓
The project involved reducing the roadway from three lanes to two, allowing for the expansion of sidewalks on both sides of Broadway. Over 98,000 square feet of sidewalk, including 3,000 square feet of colored stamped concrete, were installed to enhance pedestrian accessibility.
A notable challenge was addressing coal chutes and vault areas beneath the existing sidewalks, which provided access to basements of some historic buildings. These access points were sealed, and the cavities beneath the sidewalks were filled. KEM carefully coordinated this aspect with business owners to ensure required access while minimizing disruptions.
The project also featured the installation of new curb and gutter systems, ADA-compliant curb ramps, storm sewer upgrades, and a modern traffic signal. The outdated lighting was replaced with decorative fixtures powered by new electrical systems, while three “Festival Power Services” and three decorative LED arch signs were added. Further improvements included new brick medians at West Erie Avenue and 9th Street, along with landscaping throughout the project area.
To support local businesses, KEM worked closely with business owners to ensure safe pedestrian access to their establishments throughout construction.
KEM’s responsibilities also included daily construction inspection to verify compliance with plans and specifications, maintaining detailed logs of project activities, and verifying completed quantities. The team prepared pay requests and change orders for the owner’s approval, conducted monthly progress meetings, and performed concrete sampling and testing.