Project Details
- Client
- City of Elyria
- Location
- Elyria
- Year
- 2024
- Status
- Completed
- Photos
- 53 photos ↓
The project begins at the Black River bridge just west of the East River Street intersection and ends at the South Abbe Road intersection. East Broad Street is a major route into downtown Elyria, which includes Lorain County's administration offices and courts, and one of the main routes to University Hospitals' Elyria campus.
Construction started in July 2023 and included major improvements to the city's storm sewer and water systems. Three of the four signalized intersections received new traffic signals, and the signal at the fourth intersection was removed. All drive approaches, curbs, curb ramps, and sidewalks were replaced, and the sidewalk on the south side of the road was replaced with an 8-foot-wide asphalt multi-use path.
The project was built in two main sections. In the first, the roadway was planed, its profile corrected, and resurfaced. In the second, the pavement was removed and replaced, and the new roadway was lowered and widened to match the first section. East Broad Street now carries three lanes of traffic, with a center two-way left-turn lane.