KEM developed construction plans and provided construction oversight for the installation of approximately 2,000 linear feet of new 8-inch and 12-inch ductile iron water mains. The project scope also included replacing service lines to the right-of-way for 27 parcels, installing 5 new fire hydrants, and implementing traffic control measures to manage construction on an arterial street that terminated at one of the City's busiest intersections. Construction was strategically carried out during the winter to minimize disruptions and ensure a smooth completion.