The scope of work encompassed the demolition of the existing concrete bridge and its foundation, followed by the installation of a new 40-foot, single-span, prestressed non-composite concrete box beam bridge supported by reinforced concrete capped pile abutments. The project also included approximately 200 feet of new roadway construction and the installation of new approach guardrails.
Throughout the design process, careful consideration was given to minimizing environmental impacts and avoiding right-of-way encroachments. Enhancements were made to the roadway profile, stream hydraulics were optimized, and surface drainage was maintained consistently. Although the project required a design exception for the crest vertical curve over the bridge, the resulting configuration represents an improvement over the prior condition.