Project Details
- Client
- City of Mount Vernon
- Location
- Mount Vernon
- Year
- 2022
- Status
- Completed
- Photos
- 11 photos ↓
As an LPA Local Let Project, this initiative focused on enhancing the intersection at South Main Street and Columbus Road. Key improvements included the removal and replacement of existing traffic signals, as well as the installation of new signage and thermoplastic pavement markings.
During excavation for the final signal pole foundation, the contractor uncovered an underground fuel tank. Because the foundation was situated in the middle of a traffic island, relocation was not an option. KEM worked closely with the owner and contractor to engage a Bureau of Underground Storage Tank-certified removal contractor, ensuring compliance and safe disposal. Meanwhile, the contractor adjusted the workflow to minimize delays and mitigate potential project impacts.
The project design originally planned to reuse existing poles and raceways for new signal and lead-in cable installations at existing pedestrian signals. However, during an onsite review prior to construction, KEM identified newly installed poles adjacent to the ones slated for reuse, with some utilities already relocated to these new poles. Upon further investigation, the local power company confirmed that the existing poles were scheduled for removal. KEM promptly notified the owner and coordinated with ODOT to implement a jack-and-bore installation under the roadway, eliminating the need for overhead wiring and optimizing the final design.
KEM provided construction inspection services to ensure compliance with project plans and contract requirements. Daily documentation included written logs of project activities and verification of completed quantities. KEM also monitored subcontractor performance, ensuring contract compliance.
Additional responsibilities included conducting monthly progress meetings, approving material submittals, processing change orders, and preparing cost estimates for the City’s approval. KEM supervised concrete placement and performed quality assurance testing to ensure adherence to project specifications.